A Analysis of Preventive Maintenance Schedule of Xym1900 Vertical Roller Mill Crusher Machine using MTBF (Mean Time Between Failures) Method Based on RCA (Root Cause Analysis)
Abstract
The reliability and performance of heavy machinery are critical to maintaining consistent production in the cement industry. This study analyzes the preventive maintenance schedule of the XYM1900 Vertical Roller Mill crusher machine at PT XYZ, where frequent breakdowns have contributed to production inefficiencies and increased operational costs. The research employs the Mean Time Between Failures (MTBF) method to evaluate the reliability of key machine components and identify optimal maintenance intervals. Additionally, Root Cause Analysis (RCA) is used to trace the underlying causes of recurring failures. Maintenance and failure data were collected over a one-year period to calculate MTBF values for critical components, including the grinding roller, hydraulic system, and gearbox. RCA findings indicate that improper lubrication, delayed part replacements, and environmental factors such as dust contamination are the primary contributors to equipment failure. Based on the analysis, revised maintenance schedules were proposed to reduce unplanned downtime and extend component life. The results demonstrate that implementing a data-driven preventive maintenance plan can significantly enhance equipment reliability and support operational efficiency.
Downloads
References
Pasaribu, M. I., Ritonga, D. A., & Irwan, D. A. (2021). Analisis Perawatan (Maintenance) Mesin Screw Press Di Pabrik Kelapa Sawit Dengan Metode Failure Mode And Effectanalysis(Fmea) Di Pt. Xyz. Jitekh, 104 110.
Assauri. (1998). Pengertian Pemeliharaan ( (p. 1). https://www.kajianpustaka.com/2019/07/tujuan-fungsi-jenis-dan-kegiatan-perawatan-maintenance.html
Nuruddin, A. W. (2022). Perawatan Preventife Submersible Pump Dengan Metode Age Replacement. Prosiding Seminar Nasional Penelitian Dan Pengabdian Masyarakat, 745-749.
Rijal, M. I., Putra, A. Y., & Raihan, D. R. (2022). Analisis Perawatan Mesin Chain Scraper Conveyor Di Pt. Cemindo Gemilang Bayah. Jurnal Teknika, 191-199.
Anisa, N. (2020). Optimasi Interval Waktu Penggantian Komponen Kritis Pada Perawatan Pencegahan Untuk Meningkatkan Produktivitas. Jurnal Ilmu Ilmu Teknik, 23-27.
Muslih Nasution, Ahmad Bakhori, W. N. (2021). Manfaat Perlunya Manajemen Perawatan Untuk Bengkel Maupun Industri. Buletin Utama Teknik, 3814, 248–252.
E. Nursanti, R. M. S. Avief, Sibut, and M. Kertaningtyas, MAINTENANCE CAPACITY PLANNING Efisiensi & produktivitas. Malang: CV. Dream Litera Buana, 2019.
Ainul, F. N., & Pudji, D. W. (2020). Penentuan Interval Perawatan Mesin Air Separation Plant Secara Preventive Downtime Maintenance Dengan Menggunakan Metode Age Replacement Pada Pt. Xyz. Juminten : Jurnal Manajemen Industri Dan Teknologi, 154-164.
A. J. Wardana and M. Abdulrahim, “Strategi Meningkatkan Keandalan Mesin Reader untuk Memperpendek Antrian Pada Gate 7 Gerbang Waru Ramp,” Innov. J. Soc. Sci. Res., vol. 4, pp. 5981–6000, 2024.
Hasya, dkk 2024, “PENGARUH LIGHT SHELF STATIS TERHADAP KINERJA PENCAHAYAAN ALAMI KANTOR OPEN-PLAN ,” Jurnal Teknik Sipil Dan Arsitektur., vol. 30, pp. 2807-9418, 2025.
Wardana, A. J., & Abdulrahim, M. (2024). Strategi Meningkatkan Keandalan Mesin Reader untuk Memperpendek Antrian Pada Gate 7 Gerbang Waru Ramp. Innovative: Journal Of Social Science Research, 4(3), 5981-6000.
Budi Harja, H., Riyanto Putra, A., & Kresnandi, W. (2021). Perencanaan Strategi Preventive Maintenance Pada Mesin Shot Blasting di PT. ABC dengan Klasifikasi ISMO. Jurnal Teknologi dan Rekayasa Manufaktur, 3(1), 1–12. https://doi.org/10.48182/jtrm.v3i1.76
Andrianto, M. S., Matoati, R., & Ermawati, W. J. (2023). Revitalization of Organization and Business Determination of BUMDes Cibadak Mandiri of Desa Cibadak, Ciampea, Bogor. Jurnal Pengabdian Kepada Masyarakat (Indonesian Journal of Community Engagement), 9(1), 12. https://doi.org/10.22146/jpkm.79467
PRAFITASIWI, A. G., Kuncoro, N. R., & Wibisono, C. U. (2024). Analisa Risiko Penyebab Keterlambatan pada Proyek Konstruksi Pabrik Pupuk di Kabupaten Gresik Dengan Metode Pohon Kesalahan. Teras Jurnal: Jurnal Teknik Sipil, 14(2), 547-560.
Jensen, R.D Lucas dkk. 2011. Wear Mechanism Of Abrasion Resistant Wear Parts In Raw Vertical Roller Mills. Denmark : Technical University Of Denmark
Wang, QianHong dkk. 2012. Design and Realization Of Roller Mill Control System. China : University Of Jinan
Cheng, Kun. 2011.Finite Element Analysis For Rocker Arms Of Vertical Roller Mill On The ANSYS Workbench. China : College Of Manufacturing Science and Engineering,Southwest University Of Science and Technology,Mianyang
Mulia, N. A. C., & Rochmoeljati, R. (2021). Pengendalian Kualitas Pengelasan Menggunakan Metode Statistical Quality Control (SQC) dan Failure Mode Effect Analysis (FMEA) di PT. PAL Indonesia. JUMINTEN, 2(6), 60-71.